Manufacturing
Unified production planning for an apparel SME
28% reduction in WIP holding cost within six months

Implemented iMake to unify BOM, procurement and shop-floor production planning.
The challenge
The client ran production planning across spreadsheets and a legacy desktop module. BOM revisions were slow, procurement lagged shop-floor demand, and WIP accumulated between cutting and finishing.
Our solution
We deployed iMake with integrated BOM management, MRP-driven procurement, and mobile shop-floor reporting. Master data was migrated in phased waves with parallel run for two production lines.
Results
WIP holding cost fell 28% within six months. Planning cycle time dropped from three days to same-day refresh. Material shortages on priority styles reduced by 41%.
Technology stack
- iMake
- Node.js
- MongoDB
- React